Spanish launch company PLD Space said on October 19 that its first three Miura 5 vehicles have been built and are entering system-level testing. In the same announcement, the inaugural flight was dated to the first half of 2027. When the company unveiled its first qualification unit in November 2025, the plan was a first quarter 2026 launch. Europe's most-watched small launcher has slipped roughly a year.
Where the programme actually stands
PLD Space is running qualification and first-flight work in parallel. Two qualification vehicles and the first flight vehicle are being produced simultaneously at its 17,000-square-metre facility in Elche, so that test data feeds directly into flight hardware assembly. At Teruel, ten in-house test benches include a 10.2-metre vertical stand with an eight-metre flame duct, used for wet dress rehearsals and static hot-fires of the fully integrated second stage.
The hardware count is already substantial: seven assembled engines, 35 combustion chambers, 40 gas generators, 15 turbopumps, 13 propellant tanks, four sets of flight avionics and two fairing qualification models. About 60 containers of ground equipment have arrived at the Guiana Space Centre in Kourou to validate strongbacks, hold-down clamps and umbilical interfaces.
Miura 5 is a two-stage vehicle with a reusable first stage: 35.7 metres tall, 2 metres in diameter, five in-house TEPREL-C engines producing 190 kN each on the first stage and a single 75 kN vacuum engine on the second, burning kerosene and liquid oxygen with an optional kick stage. Published performance figures put it at roughly 300 kg to a 500-km sun-synchronous orbit — precisely the class Europe currently lacks.
Why another year
Building an orbital launcher from scratch in Europe means a long qualification chain. The flight termination system's destruct test is conducted in the United States; the first stage needs a full wet dress rehearsal; the second stage must be fired as a complete stage. Each step can push the debut back by weeks.
Money is not the constraint. PLD Space has closed a €288 million Series C round and in August 2026 won a €158.9 million contract under ESA's European Launcher Challenge to scale Miura 5 production and demonstrate reusability. Customers are queuing too: Spanish IoT constellation operator Sateliot has signed the first commercial dedicated Miura 5 mission, carrying two Tritó satellites, itself scheduled for 2027.
The constraint is time and the order in which engineering verification can happen. Rockets can be built in parallel; tests cannot be skipped.
What it means for the market
Europe's operational capacity for small satellites is thin to begin with, with Ariane 6 aimed at larger missions. Germany's Isar Aerospace reached orbit with Spectrum in September but is still in an early ramp-up. Pushing Miura 5 into the first half of 2027 leaves Europe's small-launch window empty for another year.
Customers can wait or look abroad. For European smallsat operators planning deployments in 2026-2027, the choice is stark: queue for a domestic maiden flight — which rarely carries a commercial primary payload — or turn to vehicles with flight heritage, including Electron, Indian launchers, and Chinese commercial rockets with more flexible schedules and sharper pricing.
Hanxing view
The gap between "built" and "ready for commercial customers" is measured in qualification campaigns, a maiden flight and several successful missions. Miura 5's slip is a reminder that a published debut date is only a starting point; usable capacity should be discounted by verified flights. Betting an entire deployment plan on a single unflown vehicle is the riskiest possible schedule.
Hanxing — your China launch consultancy for small satellites worldwide — helps overseas customers use that waiting period instead of absorbing it: flying pathfinders and first-batch satellites on Chinese commercial rockets through rideshare or dedicated missions, with launch consulting, orbit and separation matching, constellation deployment planning and China launch solutions that hold the timeline while domestic capacity matures.